Weekly review
Goal. Once a week, make sure the work goes according to plan, hours are logged, nobody is overloaded, and releases and projects are at the right stages.
Who does it. A project or department manager.
What you need before starting. Permissions to view projects, releases, tasks, tracks, reports, and resources. If some menu item is missing, ask the administrator: “Roles and access”.
Time. 30–40 minutes. It is most convenient to hold it on Friday or Monday morning.
Checklist
| № | Check | Screen |
|---|---|---|
| 1 | Team tasks and overdue ones | My work, “Team” mode |
| 2 | The movement of tasks through stages | Boards |
| 3 | Whether time is logged | Track hours |
| 4 | People's workload | Workload |
| 5 | Plan and fact | Resources. Plan–fact |
| 6 | Stages and deadlines of releases | Releases |
| 7 | What changed in projects | Project history |
Step 1. Overdue tasks
- Open Work → Workspace.
- Switch the mode to Team (available to the Admin and Manager roles).
- Choose the List view and the Later slice: it shows tasks with past deadlines and other late ones.
- For each overdue task choose a decision: ask the assignee to update the deadline, reassign, break into subtasks, or move to another release.
Step 2. Boards
- Open Work → Boards and choose the board you need.
- Check the columns: are there tasks that stand in one stage for a long time.
- If a task is stuck, write a comment to the assignee in the card.
Step 3. Team hours
- Open Reports → Track hours.
- Choose the period “This month” and find rows with empty days and a small sum.
- Remind employees to log time: older than 7 days cannot be logged (“Time tracking”).
- For a breakdown by project, open the “Time allocation” report, the Hours mode.
Step 4. Workload
- Open Work → Workload.
- Choose employees. On the Gantt chart, find people who have several tasks at once and those who have free windows.
- Move tasks from overloaded people to those with free capacity.
Step 5. Plan and fact
- Open Resources → Plan–fact, the current month.
- Go through the amber cells (underload) and red cells (overspend): “Resource planning”.
- For the general picture, open the Statistics tab: the target spend is 85–100% of the plan.
Step 6. Releases
- Open Work → Releases.
- Check the stage and deadline of each release. On the release's “Overview” tab you can see how many days remain at the stage.
- If a release is ready, move it on: “Closing a release”.
- If the deadline is at risk, revise the composition on the “Scope” tab.
Step 7. Changes
- Open a project, the History tab.
- Review the comments and changes for the week.
- For a detailed timeline, the administrator can use the “Audit log”.
The outcome of the week
Record the decisions with a comment in the project or release: what changed, who is responsible, and by when.
Typical mistakes
| Situation | Consequence | How to avoid |
|---|---|---|
| Review once a month | Hours older than 7 days cannot be logged | Check every week |
| Deadlines are not updated | Calendars and workload are unreliable | Require date edits when the plan changes |
| Decisions stay verbal | History is lost | Record them with a comment |